In the Phase 1 of the Mission, 950 MW solar
power projects were selected in two batches (batch-I during 2010-11 and
batch-II during 2011-12) through a process of reverse bidding. This was largely
based on the option of Bundling Scheme and on GBI option to some extent. In Phase-II Batch-I of JNNSM, the option of “Viability
Gap Fund” Scheme has been selected over reverse bidding.
Operation Guidelines of Viability gap funding under phase 2
batch 1 of JNNSM
·
The
developer will be provided a viability gap fund based on his bid. The upper
limit for VGF is 30% of the project cost or Rs.2.5 Cr. /MW, whichever is lower.
·
The
VGF will be released in following manner
1. 25% at the time of delivery of at least
50% of the major equipment at the site and after inspection by a Committee to be
constituted by MNRE. In case the inspection is taking time, SECI may release
the VGF due on self-certification by the developer against BG of equivalent
amount.
2. 50% on successful commissioning of the
full capacity of the plant. The project’s
commissioning will be declared by a Committee to be constituted by MNRE. The project would be considered as
Commissioned if energy has flown into the grid after the entire plant equipment
is installed and connected
3. Balance 25% after one year of operation
meeting requirements of generation.
·
The
tariff to be paid to the developer is fixed at Rs.5.45 per kWh. This tariff
will remain firm for 25 years project period.
In case benefit of accelerated depreciation is availed for a project,
the tariff will get reduced by 10% to Rs.4.95 per kWh in line with CERC
regulations.
·
The
developer has to put his own equity of at least Rs.1.5 Cr. /MW and the
remaining amount can be raised as loan from any source by the developer.
·
If
the project fails to generate any power
continuously for 1 year within 25 years or its assets are sold or the
project is dismantled during the tenure
of the project, SECI will have a right
to claim assets equal to the value of VGF granted and paid
Project Implementation Schedule for Solar PV Projects
Time line for Selection
of Solar PV Projects given below:
Chronicle order
|
Event
|
Date
|
1
|
Notice for request of
selection
|
Zero date
|
2
|
Submission of applications and
Techno-commercial bid
opening
|
30 days from issue of (RFS)(zero
date+30 days)
|
3
|
Short-listing of Bidders
based on
Techno-commercial
eligibility and
opening of Finance Bid
|
Within 30
days from receipt of response
to (RFS) (zero date + 60 days)
|
4
|
Evaluation of Financial
bids and
issue of letter of intent
|
Within 90
days from opening financial Bids
(zero date + 90 days)
|
5
|
PPA Signing
|
Within 30 days from the date
of issue of letter of intent
|
6
|
Financial closure of the
project
|
6 months from the date of
signing of PPA
|
7
|
Commissioning of the
Project
|
13 months from the date
of signing of PPA
|
No comments:
Post a Comment