Mr. Lavleen Singal is the Founder of Acira Solar, a solar
thermal power producer. Acira Solar has technology partnerships with
international technology companies that have been involved in the development
and operation of solar thermal power projects. Mr. Singhal also advises BRIDGE
TO INDIA on CSP.
Falling costs of concentrated solar power (CSP) development
make India a promising opportunity for this industry. However, to realize this
opportunity, some challenges need to be overcome.
Globally, CSP technology is competing with falling cost of
PV technology However, India is one of the countries that hold most
promise for CSP; it is believed that costs can be driven down significantly in
India
Unavailability of data is a significant challenge that
hinders pre project preparation – considered necessary for CSP projects
The Government of India did well to kick-start India’s
ambitious National Solar Mission (NSM) to install 20,000MW solar power projects
by year 2022. The Indian CSP industry responded with equal enthusiasm. In the
first phase, 66 bids for an aggregate capacity of 2,911MW were received against
a requirement of 470MW capacity. The LCOE of selected bidders ranged from INR10.49
(EUR0.16) per kWh to INR12.24 (EUR0.18) per kWh against a price of INR15.31
(EUR0.23) per kWh recommended by the central regulator. It signaled a welcome
phase for CSP of falling costs and sustained deployment.
Seven projects totaling 470 MW are under implementation,
with most site development work completed, installation of solar field
components commenced and all equipment ordered from the respective vendors.
Although the date for completion and commercial generation is March 31st 2013,
it is unlikely that projects will start supplying electricity to the grid by
then.
The NSM document envisages construction of up to 9,000MW
grid connected capacity by 2017. In its 9th plan document to the Planning
Commission, the Ministry of New & Renewable Energy (MNRE) has sought funds
to provide Generation Based Incentive (GBI) for 2,500MW of capacity and the
NVVN has offered to ‘bundle’ 1,500MW of this capacity. The balance capacity is
likely to be met through a strong Renewable Purchase Obligation (RPO) with a ‘bankable’
Renewable Energy Certificate (REC) scheme.
However, globally, these are difficult times for CSP. This
is due to the declining costs of PV modules. With better viability, simpler
technology, easier construction and maintenance, many developers have preferred
to convert their CSP projects to ones with PV technology. From a present
deployment of approximately 2,000MW to an anticipated 20,000MW capacity for CSP
by 2020 seems highly unlikely under the current scenario.
Nonetheless, India is one of the few countries that hold the
maximum promise for CSP projects. We can expect a deployment rate of a minimum
1,000MW per year until 2017 as well as about 500MW of pilot demonstration
projects. Additionally, Indian states are likely to implement an additional
100MW of CSP projects per year in select states where the solar resource is
good.
Policy makers in India view CSP favorably due to its ability
to ‘store’ and generate electricity when needed; hybridization with coal, gas and
biomass; and the fact that smaller plants with storage meet the needs of rural
India where it is technically and economically not feasible to supply
‘conventional’ electricity. Developers and planners also strongly believe that
the Indian industry has the capability to drive down the costs of CSP faster
than the international market. It is already known that site development, civil
works, construction, installation and commissioning costs are significantly
lower than the rest of the world. As a result, it may be possible to implement
a fully optimized CSP project within EUR2/W without storage. A typical 100MW
plant ought to cost less than INR13.5billion (EUR195m) with an expected
electricity output exceeding 200GWh/year using parabolic trough technology (without
storage) at the right locations.
Anticipating a further reduction in costs, especially for
thermal storage, CSP projects could become more feasible than at present, once
the on-going projects have been implemented and their performance gauged. It is
for these reasons that the Indian market for CSP holds the maximum promise at
this juncture. This, however, is only part of the story. Pre-project work is an
absolute necessity while planning CSP projects, particularly in India. Solar
radiation data, particularly DNI data is simply not available. Without solar
resource characterization it is nearly impossible to optimize the solar field
and thermal storage size to achieve the lowest levelized cost of electricity.
Therefore, proper site selection, land acquisition, installation of solar
meteorological stations (measuring data for at least one year), pre-project
feasibility; identification of Indian vendors and assessment of their quality,
cost and performance are some of the key pre-project issues that must be
addressed. Proper pre-feasibility studies would lead to an accurate assessment
of the ‘bid price’, but more importantly a ‘letter of comfort’ from financial
institutions for non-recourse debt financing could be one of the key metrics to
the successful development of CSP projects.
No comments:
Post a Comment